Infrastructure:

Mpatamanga Hydro Power Plant (MHPP) Project is being developed by Mpatamanga Hydro Power Limited (MHPL) in coordination with the GoM, Ministry of Energy (MoE), Ministry of Finance (MoF), and other relevant GoM departments. The project is located in the Southern Region of Malawi, within the Blantyre and the Neno Districts. The project will harness the power of the Shire River, the largest river in Malawi, lying between the existing Tedzani and Kapichira hydropower schemes. The main dam (55 m high) on the Shire River will create a 20.2 km² main reservoir at full supply level, with a total storage volume of 272.5 million m3 (out of which 58 million m3 of active volume – used in electricity generation). Water from the main reservoir will drop by approximately 66 m through underground 2x 900m long tunnels to a 301 MW powerhouse located 1 km downstream of the main dam. The water discharged from the main powerhouse into the Shire River (installed capacity of 550 m3/s) will then flow into a 1km² (total 11 million m3 / 8 million m3 of active volume) regulating reservoir created by a 45 m high regulating dam located 6 km downstream of the powerhouse on the Shire River. Water from the regulating reservoir will then be discharged into the Shire River through a 57 MW powerhouse located at the foot of the dam (installed capacity of 388 m3/s). From the upper part of the main reservoir (close to Tedzani hydropower plant) to the regulating dam, the project footprint will extend over 29 km of river length.

Energy Generation:

MHPP  will have a generation capacity of 358 MW , composed of the two plants – the 301 MW peaking plant at the main dam and the 57 MW regulating downstream plant at the regulating dam. The project is aimed to contribute to reducing energy shortages and enhancing energy security in Malawi. The 309 MW plant with its main reservoir storage is designed to provide much needed energy during peak demand hours of the day and contribute to the overall national grid stability with its ability to ramp up or down production to meet actual demand.

Transmission:

The electricity generated by the project will be delivered to the grid through two transmission lines: a 64km long 400 kV transmission line from the main powerhouse to the existing Phombeya sub-station; and an 11.4km long 132 kV transmission line that will connect the regulation dam powerhouse to the existing Tedzani-Kapichira Transmission Line.

Construction Schedule:

Technical studies are currently underway to inform the final engineering design of the Mpatamanga Hydro Power Plant and prepare the tender documentation.  

First Works (with the Construction of access roads) are planned to be undertaken from 2025. A four-year construction schedule has been estimated for the project. The power stations’commissioning should take place in April 2030.

 

Infrastructure:

A limited portion of the S137 road – which links Blantyre District to Mwanza District – will be flooded by the future Mpatamanga main reservoir. Seven kilometers   of additional road will therefore be built by MHPL to bypass the main reservoir. The S137 access road will be upgraded before the beginning of the main work

For the operations phase, a permanent operators’ village will be built close to the site, to accommodate the operators of the main dam plant and regulating dam plant. A new 6km long service road will also be built by MHPL from the main powerhouse to the regulating dam.

During the construction period the workforce will be accommodated in dedicated construction camps in close vicinity to the construction areas.

All infrastructure works are being planned, and will be undertaken, taking in consideration of both technical aspects and also environmental and social constraints. Community safety programs will also be put in place to safeguard communities during the construction and operations phases of the project.

Project Ownership and Management:

The project is to be developed on a build-own-operate-transfer (BOOT) basis by MHPL and the GoM. MHPL will be responsible for developing, constructing and operating the project for a period of 30 years , after which period it will be transferred to GoM for continued operations.

The Transmission lines will be developed and constructed by MHPL and handed over to ESCOM at the commissioning date of the power stations.